A cluster of mid‑1930s social housing terraces stabilised over six weekends, with tenants in‑situ throughout.

A cluster of mid‑1930s social housing terraces stabilised over six weekends, with tenants in‑situ throughout.
A cluster of subsidence claims across mid‑1930s social housing terraces in the West Riding. Insurers had quoted full underpinning across 14 properties at an average of £42,000 each — and the tenants were refusing to decant.
Zero tenant displacement. Works had to happen with occupants in‑situ, in‑hours, while keeping noise and dust to a minimum.
We surveyed the entire cluster against a single laser baseline, mapped the affected soil column under each property, and delivered resin injection treatment across six consecutive weekends with two crews working in parallel.
14 properties stabilised. Zero decants. Total programme cost came in roughly 64% below the underpinning quote, and the carbon footprint reduction was reported by their asset team as ≈ 95% versus the original specification.
How we work with housing associationsTell us what you're seeing. We'll book a same‑week survey, produce a written engineering report, and quote in plain numbers.